Thursday, 2 July 2009
Tuesday, 30 June 2009
[week 21] process reflection
Between the planning made in the learning plan and reality are some differences:
|
|
|
February 2008 | zoeken opdracht en verzamelen theorie | discussing materializing the pavilion as assignment | ||
March 2008 | kritische analyse opdracht en theorie | Analyzing case | ||
June 2008 | P1: voorlopig leerplan | P1:learning plan | ||
Oktober 2008 | vaststellen methode+eis | Determination criteria | ||
ontwerpen en afwegen variant | Designing options | |||
1-7 november 2008 | vaststellen te onderzoeken bouwdeel | Determination building part | ||
10-14 november 2008 | terugkoppeling onderzoek naar ontwerp | Applying research in design | ||
17-21 november 2008 | ontwerp aanpassen aan knelpunten | Design adjustments to problems | ||
24-28 november 2008 | praktische uitwerking klimaat, veiligheid, pve | Integrating functional criteria | ||
1-5 december 2008 | detailleren te onderzoeken bouwdeel | Detailing building part | ||
8-12 december 2008 | berekenen te onderzoeken bouwdeel | Calculating building part | ||
15-19 december 2008 | voorbereiden voor experimentele proef | Visualising | ||
5-9 januari 2009 | P2: leerplan en voorlopig ontwerp/onderzoek | P2: shape options and conclusion | ||
12-16 januari 2009 | voorbereiden voor experimentele proef | Analyzing problem | ||
19-23 januari 2009 | bouwen experimentele proef | Three connection problems | ||
26-30 januari 2009 | uitvoeren experimentele proef | Overview design options | ||
2-7 februari 2009 | verwerken experimentele proef | Preparation mechanical testing | ||
9-14 februari 2009 | P3: plan voor generieke kennis en toepassing | Building rib variants | ||
16-21 februari 2009 | report plan for research | testing | ||
23-28 februari 2009 | making priliminary mock ups for discussion | Functional unit, Processing test results | ||
2-7 maart 2009 | presentatie P4: definitief ontwerp/onderzoek | Options with ribs | ||
9-14 maart 2009 | verwerken commentaar P4 | Design of entire building | ||
16-21 maart 2009 | afmaken prototype/maquette | LCA comparison | ||
23-28 maart 2009 | voorbereiden presentatie | P3: plan for options | ||
30 maart - 3 april '09 | presentatie P5: conclusies, project en proces | methodology | ||
6-11 april 2009 | Generative tool | |||
13-19 april 2009 | materials | |||
20-25 april 2009 | material selection | |||
27 april-1 May 2009 | System design | |||
4-9 May 2009 | Report, Multi criteria | |||
11-15 May 2009 | Reflection and conclusions | |||
18-22 May 2009 | making priliminary mock ups | |||
25-30 May 2009 | presentatie P4: final research | |||
1-6 June 2009 | Strength and durability of Kenaf | |||
8-12 June 2009 | detail design | |||
15-18 June 2009 | Report, Multi criteria | |||
22 -27 June 2009 | Reflection and conclusions | |||
29 June 2009 | P5: making mock up |
As can be seen in the table above, some steps have started later or took longer than foreseen. This is mainly because the design process is not linear but a cycle. There have been made several options that have been tested and processed.
The colors indicate the same kind of task. Most colors occur in both planning and reality. The bright red fields indicate decision moments that have not been planned.
[week 20] multi criteria comparison
The same functional unit requirements makes it possible to compare the system designs. System design 4 is not complying to the requirement of a thin rod package because of the bracings.
There is some uncertainty in use time, dimensions and environmental index. Especially the kenaf core construction still has some uncertainties and topics for further research.
The C2C bonus is the added value of the material next to the functional unit. Biosphere materials have the possibility of energy recovering after use.
The table below compares known variables for an end grade. Higher numbers are better. Numbers are therefore normalized with best practice =1.
name | function | Environmental index | C2C bonus | total +factor |
1. technical | o | 0,19 +- 10% | O | 0,19 |
2. steel- wood | o | 0,13 +- 10% | O | 0,13 |
3. kenaf core tube | o | 0,56 +- 10% | + | 0,84 |
4. wood joints | - | 1,0 +- 10% | + | 1 |
5. solid wood | o | 0,1 +- 10% | + | 0,15 |
Because of not fitting the functional unit the wood joints are not chosen as final design.
Kenaf core tubes are the best option in total.
Thursday, 18 June 2009
Monday, 15 June 2009
[week 19] Strength and durability of Kenaf Stressed Skin Panel extrusion
design
Agricultural fibres can be pressed or extruded to plate material. The design that is elaborated here exists of kenaf particles extruded to a tube.
Kenaf (Hibiscus cannabinus) is a fast growing fiber crop related to cotton, okra, and hibiscus. The plants, which reach heights of 2,4 to 6 meters, are harvested for their stalks from which the fiber is extracted. The fiber is used in the manufacture of industrial textiles, ropes, and twines. Kenaf is among the most widely utilized of the bast fibers. (CES EDUPACk 2009)
Harvesting of Kenaf, source: http://bridgemail.bigbridge.com.au
Panasonic has set up a plant in Malaysia to manufacture kenaf core fibre boards and export them to Japan. Kenaf core fibres are comparable to hard wood. (http://en.wikipedia.org/wiki/Hibiscus_cannabinus)
source: http://www.stramit-int.com/index.html
variables
Input
Fibre type (kenaf core)
holocellulose content (71.24%)
lignin content (23.22%)
ash content (5.93%)
Kenaf core is a product from the flax plant. The properties of resin free fibreboard are superior to wheat straw, reed, palm or meadow (Jianying Xu 2006).
Fibre length (5,5 +- 2,49mm) 1,6//8 cm
Fibre length balances between modulus of elasticity and modulus of rupture.
Fibre diameter (284 +- 136 µm)fiber width (0.82–1.73 mm) cell wall thickness (3.36–5.25 lm) lumen diameter (5.82–10.39 lm)
Resin type (none)
Most fibre boards contain UF or MDI glues. Sometimes the natural lignin in the fibres can provide the necessary bonding.
Resin content (0 %)
Steam-injection during pressure -> yes
Steam injection gives better properties to the board (widyorini2005)
Pressure (0,6 MPa) 0,6/0,8
This results in a density (500 kg/m3). 300
Time of cooking (10min) 20/30
Cooking of fibres before bonding gives higher internal bonding and less thickness swelling.
Test conditions
Relative humidity (10-90%)
Outcomes
Modulus of Elasticity MOE (2,3 ± 0,1 MPa)
Modulus of Rupture MOR (19.4 ± 2,0 MPa)
Internal Bond IB (0,24 ± 0,04 MPa)
Thickness Swelling TS (18 ± 1 %)
design strength performance
height 350 mm
width 1200 mm
flange thickness 28 mm
web thickness 28 mm
Elastic deformation
MOE of 2,3 MPa results in a vertical deformation of the roof of 5/384*1,7*9000^4/ (2400*2*28*1200*175^2)= 29 mm. This is within the tolerance of 45 mm.
Long term deformation
Long term deformation caused by creep is not investigated yet. MDF shows a a comparable creep behaviour that could be studied. Conclusions from this study (Fernandez1998) are that the stress should remain below 20% of MOR to avoid rupture. Also a high relative humidity should be avoided.
Stressed Skin Panel tests with wood webs and OSB flanges showed that tests on deformation and Modulus of Elasticity showed similar outcomes (Kliger 1995).
bending strength
With a MOR of 17,4 MPa and a bending resistance of 2,1 *10^9 mm4 is a bending moment of 204 kNm possible. The designed load of 21 kNm is below this.
compression strength
The roof leans on the walls. The weight per half roof element is 70*4,5*1,2=380 kg. The surface of a wall column is 2 sides*260 depth*28 thickness=. This means that the compression force is 380*9,81/14560=0,26 N/mm2. This is below the maximum compression force of 17,4 N/mm2.
design moisture performance
Moisture and temperature conditions are calculated for worse case scenario.
inside temperature 20 oC
inside relative humidity 60%
outside temperature -10 oC
outside relative humidity 50%
To control relative humidity during high outside relative humidity, a vapour barrier around the construction could be helpful. Food industry uses bee wax coatings to improve the freshness duration.
The same wax layer on the inside and outside will trap the moisture with condensation as result.
A solution is to apply a thicker wax layer on the inside to lower the vapour pressure in the construction and insulation.
Rtot=0,04+0,06+0,06+5,00+0,06+0,10+0,13=5,45 m2K/W
Q=30/5,45=5,4 W/ m2
Tis= 20-0,13*5,5=19,3 oC -> Pio.max=2240 Ps
Tloam= 20-(0,13+0,1)*5,5=18,7 oC -> Ploam.max=2175 Ps
Twax= 20-(0,13+0,1+0)*5,5=18,7 oC -> Pwax.max=2175 Ps
Tflange= 20-(0,13+0,1+0,06)*5,5=18,4 oC -> Pweb.max=2117 Ps
Tstraw= 20-(0,13+0,1+0,06+5)*5,5= -9,1 oC -> Pweb.max=281 Ps
Tupperflange= -10+(0,04+0,06+0)*5,5= -9,5 oC -> Pweb.max=271 Ps
Tes= -10+0,04*5,5= -9,8 oC -> Pweb.max=264 Ps
Figure, Glazer diagram of vapour pressure in construction.
references
Jianying Xu. Development of binderless fiberboard from kenaf core, Journal of Wood Science, springer: Japan, 2006.
Kliger, IR, Pellicane, PJ. Prediction of Creep Properties of Chipboard Used in Stressed-Skin Panels Research scientist, Journal of Testing and Evaluation
Volume 23, Issue 6 , Chalmers University of Technology, 1995.
Ragil Widyorini, Jianying Xu, Takashi Watanabe and Shuichi Kawai. Chemical changes in steam-pressed kenaf core binderless particleboard, Journal of Wood Science. Springer: Japan 2005.
Wednesday, 10 June 2009
Tuesday, 19 May 2009
Sunday, 17 May 2009
[week 14] alternatives and conclusions
Every system design has some alternatives that I will show below. There can be made conclusions about the system, pavilion design and Cradle to Cradle.
system design 1: technical
alternatives
1 The roof cladding can be coated steel, aluminium, copper, zinc, or bitumen.
2 Insulation can be EPS, glass wool, or stone wool.
3 substructure can be steel or aluminium
4 structure can be steel or aluminium
5 interior cladding can be stone wool, perforated steel, bio-rock or gypsum board
choice
1 aluminium for its resistance to release toxic metals in the rain water.
2 glass wool for its low mass and environmental aspects
3 steel for its lower costs and environmental aspects
4 steel for its lower costs and environmental aspects
5 gypsum board for its costs
further research
The following topics can still be further elaborated:
- coatings that do not pollute underlying metals
system design 2: steel-wood
alternatives
1 The roof cladding can be wood tiles, coated steel, aluminium, copper, zinc, or bitumen.
2 Insulation can be flax wool, sheep wool, cork, EPS, glass wool, or stone wool (cellulose contains borax).
3 substructure can be fibre board, steel or aluminium
4 structure can be steel or aluminium
5 interior cladding can be wood, stone wool, perforated steel, bio-rock or gypsum board
choice
1 wood tiles for its low environmental aspects
2 flax wool for its low costs and environmental aspects
3 fibre board for its low costs and environmental aspects
4 steel
5 gypsum board for its costs
further research
The following topics can still be further elaborated:
- connection of wood shingles without steel nails
system design 3: straw board – glue
alternatives
1 The roof cladding can be wood tiles.
2 Insulation can be flax wool, sheep wool, cork, straw, or bio-EPS.
3 webs can be straw board or wood
4 flanges can be straw board or wood
5 interior cladding can be wood or gypsum board
choice
1 Wood tiles for its low environmental aspects.
2 Straw for its local availability and applying the heat resistance.
3 Straw board for the thickness and absence of glues.
4 Straw board for integration of functions and better flow of insulation.
5 Wood for its good environmental aspects.
further research
The following topics can still be further elaborated:
- market and feasibility investigation
- FJI joists with natural glues
- FJI joists with cold wood connections
- moisture and long term effects
system design 4: wood joints
alternatives
1 The roof cladding can be wood tiles or EPDM
2 Insulation can be flax wool, sheep wool, cork, or bio-EPS.
3 structure can be wood
choice
1 EPDM for its low environmental aspects
2 flax wool for its low costs and environmental aspects
3 wood
further research
The following topics can still be further elaborated:
- wood squire splice joints system design
system design 5: solid wood
alternatives
1 The roof cladding can be wood tiles or EPDM
2 Insulation can be flax wool, sheep wool, cork, or bio-EPS.
3 structure can be wood
choice
1 EPDM membrane for its low environmental aspects
2 flax wool for its low costs and environmental aspects
3 wood
further research
The following topics can still be further elaborated:
- overlapping short solid wood parts for Q-concept floors
pavilion design
The system design 4 with only wood and other natural materials does fit the criteria very well. Making the wood joints in an industrial way is also innovative.
further research
The following topics can still be further elaborated:
- climate, water distribution and building services
- finishing's with waste material
- construction of the attached glass house
Cradle to Cradle materializing
why
Savings during the exploitation of a building can be easily defended during the design phase. More difficult are savings at the end of the life span because of higher component or scrap value. But with rising prices of raw materials and awareness of the environment some attention for the Cradle to Cradle ideas worth it. Improvement of human health conditions is of importance for the user of the building. With only a small decrease of absenteeism is a large cost saving possible.
evaluation
Using materials like before the first industrial revolution will mean a more effective use of the materials. This is not always possible today. And today's designs require forms that cannot be made from only natural materials. The only way out to materialize this design is to use technical materials like recyclable watertight foil.
Does this mean that this experiment has failed because 100% Cradle to Cradle is not achieved? In my opinion not because it shows that innovation can reach the destination at the end. This may be done in little steps but is must happen if we want to give our children the same opportunities that we have.
SWOT
strengths
- willingness of parties
- better performance than practice as usual
weaknesses
- not objective without quantitative comparison
- commercial background of certification
opportunities
- future benefit
- simplification of details with less cost
threats
- building regulations
- extra costs
further research
This research is not complete and raises more questions than answers. Further research could go in to the following topics:
Friday, 24 April 2009
[week 12] building the prototype
system design 3
It will be made of straw board attached to the soft wood flanges with natural glue.
Figure 12.1, axonometry of system design 3
For a specimen scale 1:2 (35x180x4500 mm) will be needed:
- straw board 6x200x4500 mm
- soft wood 2x 2335x4500 mm
- glue 2x 4.5x25 grams
Figure 12.2, preperation for a scale model 1:2 of system design 3
system design 4
It will be made from only wood and other natural materials.
Figure 12.3, section of system design 4
For a specimen scale 1:1 (75x275x2000 mm) will be needed:
- soft wood 3x 75x275x1200 mm
- soft wood sub beams 50x50x1000 mm
Figure 12.4, testing a scale model 1:5 of system design 4
Thursday, 16 April 2009
[week 11] LCA comparison
1. steel
weight | E costs | |||
Steel coated, corrugated | 8.60 | kg/FE | 0.02 | (eur/year) |
glass wool 150 | 7.50 | kg/FE | 0.01 | (eur/year) |
VAPOUR BARRIER | 1.00 | kg/FE | 0.00 | (eur/year) |
corrugated steel filling | 10.92 | kg/FE | 0.12 | (eur/year) |
Steel beam Hea 260 | 8.35 | kg/FE | 0.10 | (eur/year) |
gypsum board 12mm | 1.56 | kg/FE | 0.02 | (eur/year) |
total | 37.93 | kg/FE | 0.28 | (eur/year) |
Figure 1, life cycle and sub cycles of steel beams.
1.1 life timeThe durable materials will make a longer life of components possible. A technical life of 105 years is realistic with components that last three building uses. The total environmental effects will be divided over this technical life for the effects per year.
1.2 construction strength
If the bay distance is two meter, than 260 mm high beams are sufficient.
1.3 thermal insulation
The 150 mm glass wool results in an Rc value of 4. 1 m2K/W.
2. steel-wood
Wood shingles 2x 9 mm | 8.64 | kg/FE | 0.01 | (eur/year) |
plate straw 18 | 8.1 | kg/FE | 0.01 | (eur/year) |
glasswool 280 | 14.00 | kg/FE | 0.02 | (eur/year) |
VAPOUR BARRIER | 1.00 | kg/FE | 0.00 | (eur/year) |
plate corrugated | 9.00 | kg/FE | 0.18 | (eur/year) |
steel C360/100/38 x 2,5mm | 12.21 | kg/FE | 0.14 | (eur/year) |
0.00 | (eur/year) | |||
total | 52.947 | kg/FE | 0.35 | (eur/year) |
2.1 life time
disassembling possible for reuse: yes
lifetime: 2 building uses = 70 years
Only the wood shingles should be replaced after one building use.
2.2 construction strength
The steel C profiles are spanning the building every meter.
thickness | 2.5 mm | |
dimensions | C360/100/38 mm | |
dead+live load | 1.5 kN/m2 | |
bending moment | 15.2 kNm | < mmax =" 24"> |
2.3 thermal insulation
The FlexFrame system can fit the criteria if the insulation is thick enough. Because the steel profiles form linear cold bridges of 2.5 mm every meter the thickness of insulation has to be double of the thickness without the cold bridges. Together with 18 mm straw board and wood shingles on top there will be a heat resistance of 4.1 m2K/W.
3 laminated beams
An m2 of roof consists of
EPDM-membrane 1.14 mm | 1.41 | kg/FE | 0.05 | (eur/year) |
plate straw 18 | 8.64 | kg/FE | 0.01 | (eur/year) |
flax wool 140 | 7.00 | kg/FE | 0.02 | (eur/year) |
FJI joists | 4.93 | kg/FE | 0.03 | (eur/year) |
Vapour barrier | 1.00 | kg/FE | 0.00 | (eur/year) |
batters 38x50 /1,2m | 0.7125 | kg/FE | 0.00 | (eur/year) |
gypsum | 1.56 | kg/FE | 0.06 | (eur/year) |
25.25 | kg/FE | 0.17 | (eur/year) |
3.1 life time
Technically these materials could be reused after 35 years. But this would need more labour than new materials. That is why only one building use is prognosed.
3.2 construction strength
If the bay distance is 0.3 m, than 380 mm high FJI-beams are sufficient.
3.3 thermal insulation
The FJI-beams are negligible as cold bridge. The space in between can be used to place 140 mm flax wool insulation that results in an Rc value of 4. 0 m2K/W.
3 wood joints
4 solid wood
Thursday, 9 April 2009
Sunday, 29 March 2009
[week 9] building variants with ribs
1. steel
If the bay distance is two meter and the infill corrugated steel, than 260 mm high beams are sufficient. The system that is uses is called Planja.
2. steel-wood
These elements from steel C-profiles and wood board cladding are made by the manufacturer FlexFrame.
3. wood I-joists
Like in a Passive house, these high I shaped beams can be put every 300 mm with insulation in between.
4. wood joints
Inspired by traditional techniques and with the use of industrial production. Elaboration will follow.
5. solid wood
This system is brought on the Dutch market by Q-concept and declared as best floor from LCA viewpoint ().
Friday, 27 March 2009
[week 8] functional unit
These variants can be compared with a Life Cycle Assessment on environmental impacts. A strict boundary will be needed to compare them with the same functional unit.
The functional unit is 1 m2 roof including:
* boarding, insulation, waterproofing and inside finishing
* construction of beams and connections equally distributed over 1 m2
The variants are:
* steel construction with 200mm glass wool insulation and gypsum inside finishing
* wood-steel hybrid that can be disassembled or incinerated
* wood laminated beam that can be incinerated
* wood and natural adhesives that can be composted
* massive wood as single material
An interesting variant that can be ad:
* bio based composite with soy oil and flax fibers
Friday, 20 March 2009
[week 7] testing
The variants are now tested on bending strength. The supporting points are 2.8 meter from each other. The load is spread over two points 0.7 meter from each other.
Variant 1 is the existing reference inspired by the Q-concept. The max load before collapsing is 9350 N. The area is 0,9 m2 so it is more than 1 kN per m2. Also bending is minimal. And collapse is announced by a lot of cracking.
Figures variant 1 during collapse.
Variant 2 was already bending under its own weight. The weak point is the combination of bending and shear force that lets the week point of the connection splice apart. The maximum resistance was 323 N.
Figures variant 2.The biggest problem with variant 3 was that the bottom flenge gets loose from the web because its own weight. Especially with the dove tails that act like a hinge but also during the second attempt without the dove tail connection is mostly resisted with the web strengths. The max resistance was 833 N.
Figure variant 3.